M/T THERESA MARS
★Combustible gas detect system to be calibrated
★A/E safety protection alarm system to be checked and repaired
★Fire alarm system repaired
★Cargo tank H.L. &H.H.L.alarm system to be checked and tested.
★Cargo tank H.L. &H.H.L.alarm system to be repaired.
★Cargo tank level indicator system to be checked and calibrated
★Ullage-Temperature-Interface Detector checked and calibration
★Ullage-Temperature-Interface
★Cargo tank pressure indicator system to be checked and calibrated
★The boiler control system checked and repaired
★M/E shaft bushing temperature detect system installation
★Pump room fire detector installation.
★Oil content meter checked and calibrated (type: OMD-2005)
★Deck air compressor control system repaired.
★1#、2# boiler feed water pump control system repaired
★M/E sea water pump control system repaired
★1# fuel oil supply pump control system repaired
★2# M/E F.W. pump control system repaired
★Feed oil pump for power pack repaired
★1# engine room fan control system repaired
★2# engine room fan control system repaire1
★Potable water pump control system repaired.
★Sea water general pump control system repaired